Indian Oil Corporation Limited (IOCL)-Vijaywada

Design, Supply, Installation, Testing & Commissioning of PLC System and HMI SCADA with Web-Based Platform for Signal Sharing with GAIL at Hyderabad and Vijaywada LPG Bottling Plants

  • Client : Indian Oil Corporation Limited (IOCL)-Vijaywadad
  • Location: Hyderabad and Vijaywada, Andhra Pradesh
  • Industry : Petroleum refining and Marketing

Project Scope

  • Design: Detailed design of the PLC system and HMI SCADA.
  • Supply: Procurement of all necessary materials and equipment.
  • Installation: Setting up of the PLC system and HMI SCADA.
  • Testing & Commissioning: Conducting thorough tests to ensure the system operates efficiently and safely.
  • Web-Based Platform: Development of a web-based platform for real-time data sharing with GAIL.

Detailed Scope of Work

  • Pressure Transmitters:
    • Supply of 8 pressure transmitters.
  • Temperature Transmitters:
    • Supply of 14 temperature transmitters.
  • Cables and Accessories:
    • Supply and installation of armored cables, signal cables, multicore 24-core cables, RJ11 cables, connectors, pigtails, junction boxes, cable trays, limit switches, and other accessories.
  • PLC System:
    • Supply and installation of PLC with CPU, I/O modules, and programming software.
  • SCADA Software:
    • Supply of unlimited tags SCADA software development license.
  • PLC Panel:
    • Supply and installation of PLC panel.
  • Signal Cables:
    • Supply and installation of 24-pair multicore signal cable for transfer of signals to GAIL panel room.
  • Web Space Enabler:
    • Supply and installation of web space enabler for real-time data sharing with GAIL.
  • SCADA Software License:
    • Supply of SCADA software license for unlimited tags client.
  • Desktop PCs:
    • Supply and installation of desktop PCs with authorized operating system license.
  • Application Development:
    • Customization of SCADA software, development, installation, commissioning, and documentation.
Installation
  • PLC System Installation:
    • Installation of PLC system at both Hyderabad and Vijaywada sites.
    • Ensuring all connections are secure and meet safety standards.
  • HMI SCADA Installation:
    • Installation of HMI SCADA system.
    • Integration with the web-based platform for real-time data sharing.
  • Cable Installation:
    • Laying of armored cables, signal cables, multicore 24-core cables, and RJ11 cables.
    • Installation of connectors, pigtails, junction boxes, cable trays, and limit switches.
Testing & Commissioning
  • System Testing:
    • Testing of all electrical systems, including PLC and HMI SCADA.
    • Verification of protection relays and circuit breakers.
    • Load testing to ensure the system operates efficiently under load conditions.
  • Commissioning:
      Commissioning of the entire system to ensure it is fully operational.
    • Final checks and balances to ensure all systems are running smoothly.
    • Handing over the system to IOCL with all necessary documentation and as-built drawings.

Challenges Faced

Technical Challenges
Regulatory Compliance

Overcoming Challenges

Technical Expertise
Regulatory Compliance

Project Completion and Handover

We are proud to announce that this project has been successfully completed, meeting all the specified requirements and timelines. Our team’s dedication and expertise ensured seamless execution and delivery, contributing to the robust power infrastructure of the region.